Education 2020: 色中色 Capital Project
色中色 voters approved this capital project on March 14.
Yes: 383
No: 111
As the 色中色 continues to make progress with the second phase of the Education 2020 implementation, it also is working to develop a deeper understanding of the programmatic and facility improvements necessary to serve the 色中色 community into the future. As part of this initiative, the district is working to utilize resources available to not only address facility needs, but to advance the educational direction of the district.
To that end, the 色中色 CSD has scheduled the Education 2020: 色中色 Capital Project Vote for Monday, March 14. Voting will take place from 6 a.m. to 9 p.m. in the Wetzel Road Elementary gymnasium.
.
Read the Capital Project issue of the School Bell online now!
Project Schematics
Timeline
- January 24, 2022: Board Resolution/SEQRA Approval
- February 9, 2022: Public Presentation at the 色中色 Public Library beginning at 6:30 p.m. (during regularly scheduled Board of Trustees Meeting)
- February 25, 2022: School Bell Mailed to Community
- March 8, 2022: Public Hearing at District Office beginning at 6 p.m.
- March 9, 2022: Public Presentation at 色中色 beginning at 6:30 p.m.
- March 14, 2022: Capital Project Vote at Wetzel Road Building from 6 a.m. to 9 p.m.
Scope of the Proposed Project
Cost: $72,184,922
Financed by:
- Capital Reserve Funds (2015-16 & 2020-21)
- State Education Department Building Aid
-
No Additional Cost to Taxpayers
The proposed capital project will impact five district facilities:
色中色
- Major Renovations of the center stack (100s, 200s and 300s)
- Main Entrance and Canopy Additions
- Cafeteria and Kitchen Renovations
- Air Conditioning in Portions of the Building
- Science Room Upgrades
- Site Work
- Track & Field Upgrades including Synthetic Turf Replacement
Morgan Road Complex
- Band Room
- Orchestra Room
- Site Work
- Parking Lot Expansion
- Synthetic Turf Softball Field
- Drainage Improvements
Wetzel Road CTE Academy
- Technology Education Classrooms with High Bay Addition
- FACS Classrooms
- Culinary Lab
- Fashion Design Lab
- Broadcast and Media Marketing Classrooms
- District Office Improvements
- Site Improvements
- Synthetic Turf Baseball Field
Long Branch Elementary & Transportation Center
- Site Work
- Drainage Improvements
- Redesign Parking Lot with Dedicated Bus Loop